Procurement of Packaging Materials in the Vaccine Industry: More Planning Than Procurement
- adhiraj thote
- May 16
- 3 min read
During my four years in materials planning and procurement for packaging materials in the vaccine industry, one realization stood out very early — the role was far more planning-intensive than traditional procurement.
On paper, procurement appears to be about raising purchase orders and negotiating with suppliers. In reality, especially in a highly regulated industry like vaccines, procurement becomes an extension of production planning, inventory management, supplier capacity planning, and stakeholder coordination.
As a Procurement Executive, my responsibility started much before issuing a Purchase Order.
The process began with receiving a three-month rolling filling plan from the Sales & Operations Planning (S&OP) team. This plan included the projected production schedule for multiple vaccine SKUs across filling plants.
The next step was to map each product with its corresponding packaging materials such as:
Glass vials
Rubber stoppers
Ampoules
Diluent bottles
Labels
Cartons
Inserts
Based on the product mix and batch sizes, we converted the production plan into a detailed Material Requirement Plan (MRP) for the upcoming months.
The planning horizon itself required careful synchronization:
Materials with a 45-day lead time were planned for M1 and M2 during M0
Materials with a 90-day lead time were planned for M3 during M0 itself
This meant that procurement decisions were effectively dependent on forecast accuracy, production stability, supplier reliability, and inventory visibility.
In many situations, stakeholder coordination became more critical than procurement execution.
For example:
Packaging material consumed at subcontracting filling plants was often not directly visible in the central inventory system
Stocks transferred to substores were sometimes unavailable in real-time inventory reports
Production plan changes required immediate remapping of packaging material demand
Any mismatch between production scheduling and packaging material availability could directly impact vaccine dispatch timelines
Below is a simplified representation of how planning was typically structured:
FG Product | Filling Plant | Material Required | Min RL | Max RL | Subcontracting Plant | Current Stock | Filling Plan (June) | Filling Plan (July) | Lead Time | Supplier Status | Key Risk | Action Taken |
Vaccine A | P2 | 10ml Glass Vials | 60 | 90 | - | 52 | 20 | 24 | 45 Days | On Track | Capacity Constraint | Blanket PO Released |
Vaccine B | P1 | Rubber Stoppers | 40 | 70 | P5 | 28 | 18 | 22 | 45 Days | Delayed | QA Rejection Risk | Alternate Vendor Activated |
Vaccine C | P3 | Printed Cartons | 100 | 160 | - | 82 | 40 | 35 | 30 Days | On Track | Artwork Revision | Revised Forecast Shared |
Vaccine D | P4 | Ampoules | 50 | 80 | P2 | 20 | 16 | 24 | 90 Days | Critical | Import Delay | Internal STO Planned |
Vaccine E | P2 | Labels | 75 | 120 | - | 64 | 32 | 28 | 20 Days | Stable | Demand Volatility | Safety Stock Increased |

Once the plan was finalized, it went through approvals from:
Team Leads
Department Heads
S&OP stakeholders
Post approval, we validated:
Open Purchase Orders
Current inventory
In-transit stock
Reorder levels
Pending Purchase Requisitions (PRs)
For high-volume and fast-moving SKUs, we often created blanket Purchase Orders aligned with annual demand projections received from the S&OP team. This reduced procurement cycle time and helped suppliers reserve production capacity in advance.
The Purchase Orders then moved through multiple release stages involving:
Audit teams
Team Leads
HOD approvals
Only after these approvals were POs released to suppliers.
However, supplier management truly began after PO release.
We regularly conducted supplier alignment calls to discuss:
Production schedules
Dispatch planning
Capacity bottlenecks
Batch prioritization
Upcoming demand spikes
Whenever a supplier was unable to meet the committed schedule, we generally explored two contingency options:
Procurement from another approved vendor
Internal stock transfer between plants
Both options came with operational complexities.
Internal stock transfers required alignment between:
Product stakeholders
Warehouse teams
S&OP teams
Logistics teams
In certain cases, stock transfer from SEZ units to EOU units was restricted due to EXIM compliance limitations.
Alternate sourcing also had its own challenges.
Some stakeholders strongly preferred specific vial vendors because of historical quality performance and process familiarity. Even when alternate vendors were technically approved, operational teams were sometimes hesitant due to previous rejection experiences.
In situations where:
Alternate vendors were unavailable
Stock transfer was not feasible
Demand was business critical
…the only remaining solution was supplier capacity negotiation.
Since we maintained long-term strategic relationships with several packaging vendors and committed significant annual business volumes, we were often able to negotiate additional production allocation during critical demand periods.
Before dispatch, suppliers typically shared pre-dispatch documentation such as:
Delivery Challans
Test Certificates / COA (Certificate of Analysis)
E-way Bills
Packing Lists
Invoice Copies
Batch Traceability Documents
After verification, we coordinated dispatch confirmation and informed warehouse teams to prepare for Goods Receipt (GR) processing and inward inspection.
Looking back, the role taught me that procurement in the vaccine industry is not merely transactional purchasing. It is a continuous balancing act between:
Forecast accuracy
Inventory optimization
Supplier capacity
Regulatory compliance
Production continuity
Cross-functional stakeholder management
The real value was not in placing Purchase Orders, but in ensuring that a single missing packaging component never became the reason a vaccine batch could not be filled or dispatched.



Very detailed and easy explanation! 👍🏻 The role looks really interesting.